Bulletin
Organisation:
The public is notified that works on the recently signed contract for the nine (9) miles of road paving from West End to Road Town will commence in the area of Coxheath and the Bluff for four thousand (4000) linear feet of stone revetment works, repairs to the sea defence walls to protect the shoreline with subsequent concrete pavement works to follow.
Works are slated to commence on Saturday 17th January with heavy equipment and trucks operating in the area. Motorists are asked to exercise caution while traversing the area and follow all signage and traffic personnel.
Works in the area are slated to last for a period of two (2) months. Any inconvenience caused is regretted.
For Additional Information Contact:
Paul Bridgewater
Information Officer
Department of Information and Public Relations
Telephone: 468-2747
Email: pbridgewater@gov.vg