Installation of a standby generator must be pre-approved by the Government. The standby generator is only to be used when the BVI Electrical Corporations current is off.
Process
Step 1: Applicant submits form to the Ministry of Communications and Works in hard copy.
Step 2: The Electrical Inspections Unit would contact the applicant to arrange the site visit.
Step 3: Once approved, a letter of approval would be issued to the applicant from the Ministry of Communication and Works.
Supporting Documents
- Application Form
Turn Around Time
21 days
Additional Notes
Once the original installation is to be changed or modified, the applicant is suppose to inform the Electrical Inspections Unit.
Department Contact Information
Ministry of Communications and Works
Business Hours:
Monday - Friday
8:30 a.m. to 4:30 p.m.
Email Address: mcw@gov.vg
Telephone: 1(284) 468-2183
Fax: 1(284) 468-3090